Thursday, August 30, 2012

Now there's a structure to step onto when I open the door from the kitchen on the 2nd floor of 1700 Vine St! When all is said & done, this will have a roof deck & be immediately accessible from my kitchen.

The new addition

The new addition between the two buildings is really taking shape! This will hold a new staircase for the Hamer St building, storage, house 2 rain water retention tanks and enable us to interface with our green space. Is a roof deck on top of thus structure.

Thursday, August 23, 2012

Saturday, August 18, 2012

Many trucks = lots happening!

Two crews are working today, masonry & carpentry.

Thursday, August 16, 2012

Saturday, August 4, 2012

South wall is going up

This will end up about 3' above the 2nd floor so that it acts as a railing on the new deck.

Thursday, August 2, 2012

Building the new addition

The footers are poured and the concrete block is going up.